Satellite Goods Terminal (SGT) Proposed augmentation of infrastructure facilities
for capacity enhancement of SGT wagon depot to meet demand of freight loading
of 3000 MT target by 2027. SW-I Proposed shed extension by 50m at WFD end at
SGT and construction of 26m pit in sick line no.2 at WFD end at SGT. SW-II
Proposed re-surfacing of trolley path of 4 yard examination lines and pathway to
PWL shed to new office complex (8400sqm). SW-III Proposed demolition of
existing building to extend the ROH shed towards Whitefield end and clearing the
debris 22x5mtr (G+1) 220sqm. SW-IV Proposed construction of admin building on
existing mechanical building FF-252sqm. SW-V Proposed provision of side
transparent sheets in existing old shed portion at SGT. SW-VI Proposed
construction of room for MFD items at SGT. SW-VII Proposed construction of scrap
yard with RCC heavy duty flooring with waist level 3 side wall at SGT. SW-VIII
Laying of track and connected works. SW-IX Satellite Goods Terminal (SGT) RCC
Buffer - 2 nos. Maintenance period is 12 months. COMPOSITE TENDER.
|
Tender Detail : |
Satellite Goods Terminal (SGT): Proposed augmentation of infrastructure facilities
for capacity enhancement of SGT wagon depot to meet demand of freight loading
of 3000 MT target by 2027. SW-I: Proposed shed extension by 50m at WFD end at
SGT and construction of 26m pit in sick line no.2 at WFD end at SGT. SW-II:
Proposed re-surfacing of trolley path of 4 yard examination lines and pathway to
PWL shed to new office complex (8400sqm). SW-III: Proposed demolition of
existing building to extend the ROH shed towards Whitefield end and clearing the
debris 22x5mtr (G+1) 220sqm. SW-IV: Proposed construction of admin building on
existing mechanical building FF-252sqm. SW-V: Proposed provision of side
transparent sheets in existing old shed portion at SGT. SW-VI: Proposed
construction of room for MFD items at SGT. SW-VII: Proposed construction of scrap
yard with RCC heavy duty flooring with waist level 3 side wall at SGT. SW-VIII:
Laying of track and connected works. SW-IX: Satellite Goods Terminal (SGT): RCC